Tucson Electric Power Standards

A contractor’s hub for TEP service, metering, and interconnection — the official documents, the requirements we field most, and an assistant grounded in TEP’s published guidance. TEP’s standards change, so the official documents and TEP are always the final word.

Always Current

Official TEP documents

These link straight to TEP’s own pages and current publications. Individual standard sheets (SR-405 metering, SR-414 CT metering, SR-600 grounding, and the rest) live inside the 2026 ESR Book. Note: TEP publishes the book annually (around March) and keeps revising afterward — check the Monthly Summary of Revisions on the ESR portal for changes made after the book published. If something looks off, confirm directly with TEP service planning.

New to the TEP process? Start with our plain-language companion guide — TEP new service requirements for commercial projects — which walks the whole flow from application to energization before you dig into the standard sheets.

From TEP’s Published Guidance

Requirements we field most

Quick reference based on TEP’s published guidance — confirm the current edition with TEP before you build to it.

Metering

  • TEP supplies the meter — the meter socket / panel is the customer’s or contractor’s responsibility, and it must be on TEP’s approved list (SR-452 above).
  • Meter height — center of the meter generally 3′6″ min to 6′3″ max above final grade.
  • Multiple meters — each panel permanently marked (not painted), typically 1/4″ min letters on a non-ferrous tag riveted to the panel.

CT / commercial metering

  • Larger commercial services beyond self-contained meter ratings use instrument-transformer (CT) metering — socket requirements are in sheet SR-414 and CT cabinet installation, conduit, and clearance details in sheet SR-422, both inside the 2026 ESR Book above.
  • CT cabinet conduit — TEP’s guidance commonly requires service conduit from the CT cabinet to be IMC or RMC to a minimum of 18″ below final grade. Confirm in the current sheet.

Underground service & trenching

  • Who does what — the customer/contractor typically provides the trenching, conduit, backfill, and surface restoration; TEP furnishes, installs, owns, and maintains the underground service cable to the approved termination (Rules 906).
  • Before you dig — call Arizona 811 (Blue Stake) for utility locates. We self-perform this trenching and conduit work daily with our own crews and equipment.

Grounding & inspection

  • Grounding electrode conductor by service size#6 solid copper for 100–125 A services; #4 AWG copper for 150–200 A services (per NEC Table 250.66, which TEP’s grounding sheet SR-600 defers to, as enforced locally). SR-600 also requires a GEC run without conduit to be at least #4 copper, and any GEC smaller than #4 to be solid copper.
  • Ground rods — two 8′ × 5/8″ rods are the local norm; SR-600 requires rods at least 6′ apart with at least 8′ in contact with the soil. Confirm against the 2026 ESR Book and the NEC.
  • Inspection commonly checks — meter sockets, connections, trenches, conduit, and address / panel labeling.

Working in Trico territory? TEP doesn’t serve the whole metro — Trico Electric Cooperative serves areas including much of Marana, Corona de Tucson, and other outlying areas, and has its own service requirements. Confirm which utility serves your site before building to a standard.

Approved Equipment

TEP approved panels & meter equipment

TEP publishes its approved metering service equipment in standard sheet SR-452 — the authoritative list of meter sockets and metering equipment accepted for purchase or stock, covering 0–200 A and 201–400 A single- and three-phase services. TEP republishes it quarterly (January, April, July, October), so always use the posted sheet, not a cached copy.

The Official List

SR-452 — Approved Metering Service Equipment

TEP’s reference list of approved equipment, straight from the ESR book.

Spec It Right the First Time

Not sure what passes?

We spec, procure, and install TEP-accepted metering and service equipment on commercial projects every week — ask the assistant below, or have our team review your service spec before you buy gear.

The Process

Getting a new commercial TEP service — the typical flow

Every project differs and TEP’s process governs, but a new or upgraded commercial service usually moves through these steps. Build the lead time into your schedule — utility design and equipment are often the long poles. For the step-by-step version in plain language, see our TEP new service requirements guide.

1 · Apply

Construction application

Submit TEP’s construction application with site plan and load information. Earlier is better — this starts TEP’s design clock.

2 · Design

TEP design & point of connection

TEP service planning designs the service, sets the point of connection and transformer location, and identifies any easements required.

3 · Build

Trench, conduit & equipment

The contractor installs the trench, conduit, pads, and metering equipment to TEP’s spec — using gear from the approved list (SR-452). Call Arizona 811 before digging.

4 · Inspect

Inspections & corrections

The AHJ and TEP check the installation — sockets, connections, trench and conduit, labeling. Corrections here are the most common schedule slip.

5 · Energize

Meter set & release

TEP pulls in or terminates its service cable, sets the meter, and releases the service — the site goes live.

Or

Let us run it

We handle the application, utility coordination, trenching, and installation as one self-performed scope. Request a bid.

Ask

TEP Standards assistant

Ask about TEP service, metering, CT installations, trenching responsibilities, grounding, or interconnection. The assistant answers from TEP’s published guidance above — with direct links to the right standard sheet — and points you to TEP for anything it can’t confirm. It won’t guess equipment models or revisions. When an answer comes from a specific standard sheet, the assistant shows a snapshot of that page with a link straight to it in the official book — no scrolling through a 100-page PDF.

TEP Assistant
Hi — ask me about Tucson Electric Power service, metering, CT installations, trenching, grounding, or interconnection. I answer from TEP's published guidance and link you straight to the right standard sheet (including SR-452, TEP's approved metering equipment list). I won't guess equipment models or revision numbers — for those I'll point you to the official document or to TEP.
Try:

How it works & please verify. The assistant is grounded in TEP’s published guidance (linked above), not guesswork — for the approved-equipment list, exact revisions, or commercial tables, it points you to the official TEP document or to confirm with TEP. TEP standards change; the official documents and TEP service planning are always the final word. This is a contractor convenience, not an official TEP publication. Arizona Electrical Solutions is not affiliated with or endorsed by Tucson Electric Power.

Coordinating a TEP service for a commercial project?

We handle utility coordination, point-of-connection, metering, and the install — self-performed across Arizona.

Request a Bid