  • Electrical service: no service or panel permit on record. A 1951 house likely still has its original 60 to 100 A service.
  • Watch for: built 1951, when Federal Pacific and Zinsco panels were sold. Worth a look at the panel label.
  • Other work on record: solar added 2018, AC installed 2017.

From City of Tucson permits and the Pima County Assessor, checked 13 Nov 2026. Not an inspection.

I am a
Get a free panel check

Is it time to upgrade?

Likely yes: no service upgrade is on record for this 1951 house.

  • Electrical service & panelLikely needs attentionNo service or panel permit on record. A 1951 house likely still has its original 60 to 100 A service. The panel makes and wiring methods of that era are what the era notes below flag, and only a look at the panel settles it. Worth knowing: a 2018 solar pv permit is on file — work like this is often folded into a larger permit without being named, so open that record and check its scope before concluding anything.
  • Heating & coolingLooks currentLast permitted 2017 (9 years ago) — the permit passed final inspection. The assessor still records cooling as Evaporative; the 2017 permit is the newer evidence (assessor characteristics can lag permitted work). Cooling equipment works harder in Tucson than almost anywhere, so 12 to 15 years is a realistic service life rather than the 15 to 20 the industry quotes. T17CM02793 — Remove existing evaporative cooler & furnace & install 4 zone ductless AC system. Provide wp disconnect at condenser
  • Water heaterWorth checkingNo permit on record names this system. Water heaters are frequently swapped without a permit, so this line is especially weak evidence either way.
  • RoofWorth checkingNo permit on record names this system. The assessor records the roof as Asphalt.

What that usually means electrically

  • Era-based check — high priority

    60–100 A was standard. That is enough for a mid-century house, not for a modern kitchen, HVAC, and an EV.

  • Era-based check — high priority

    Federal Pacific (Stab-Lok) and Zinsco/Sylvania panels were sold through this period. Stab-Lok breakers have a documented history of failing to trip internally; Zinsco breakers can weld to the bus so the handle moves without breaking the circuit. In both cases a replacement breaker does not resolve it — the panel itself is what gets replaced.

  • Era-based check

    Grounded branch circuits did not become the norm until the early 1960s — much of the original wiring here is likely ungrounded.

  • Era-based check

    Cloth-jacketed NM cable is common in this era. The jacket embrittles with age and heat, particularly in Tucson attics.

What to check at the panel

These are the things only someone standing at the panel can settle — about a minute’s work.

  1. The number stamped on the main breaker handle — 100, 125, 150, 175 or 200. That is the service rating, and no record on this page confirms it.
  2. The busbar rating printed on the panel label. It is a different number from the main breaker, and it is the one that decides how much solar a panel can take under the 120% rule.
  3. The manufacturer and catalog number on the label inside the door.
  4. How many full-size spaces are left, how many positions the label permits a tandem breaker in, and the tandem limit the label states. A full panel is a different job from a full service.
  5. The conductor material at the main lugs, and whether the terminations look clean and tight.
  6. Whether there is a separate meter-main outside as well as the panel indoors — that changes where a disconnect and any new feeder would land.
  7. Whether the water heater, dryer and range are gas or electric. No public record carries fuel type, and it is the single biggest variable in a load calculation — it can move the calculated load on the same house by more than 40 A.
  8. The brand on the door or the breaker faces. Federal Pacific panels usually read “Federal Pacific Electric” or “FPE”; Zinsco panels read “Zinsco”, or on later stock “Sylvania” or “Sylvania-Zinsco”. Finding a Square D, Eaton, Cutler-Hammer, Siemens or GE panel here is the ordinary result and is not a finding — those are current, supported lines with breakers on the shelf.
  9. Whether receptacles are two-prong, and whether any three-prong replacements have an actual ground behind them. A $10 tester answers this at every outlet.
  10. Whether the kitchen counter, bathroom, garage and exterior receptacles have GFCI protection, and whether the test button actually trips them.

With those in hand you can run the numbers yourself. The load calculator does the NEC 220.82 optional-method calculation — the same method a permit application uses — and shows its work. It offers to start from the 994 sq ft on the assessor record; every other value is yours to enter. Open the load calculator

What these jobs cost here

The cooling equipment here was permitted in 2017 — replacement is not due yet.

Electrical panel or service upgrade Estimate

$3,800

Most jobs like this land between $3,400 and $4,700.

The bottom of this range is a clean, simple job: single storey, framed wall, the panel staying where it is, a short service run, and nothing unexpected once the cover comes off. That job is real and we do book it — but it is the best case, not the average, and the figure above it is what most houses actually come to.

Priced from built 1951 (post-war 60–100 A service era); City of Tucson permit fee and the 2023 NEC it has adopted.

Priced with Tucson Electric Power’s charges — TEP serves the City of Tucson.

What would move this price
  • Only if the panel has to move — a clothes closet, a bathroom, over a stairway, or behind a door +$3,900
  • Only if the mast is undersized or corroded — common at this age +$1,300
  • Only if the metal water and gas piping are not already bonded — usually not, at this age +$600
  • Only if the original fuse or split-bus panel is still in service +$1,700
  • Only if the walls are block or adobe rather than framed — the county record does not say which +$1,100
  • Only if stucco has to be cut and patched +$1,100

If every one of those turned out to apply, this becomes about $14,300. That is the worst realistic case.

Before you spend anything
  • A service upgrade fixes capacity and the safety of the service equipment. It does not fix branch wiring. If the reason you are here is flickering lights, warm outlets or cloth-jacketed wiring, an upgrade is a down payment on a much bigger problem, and it is worth knowing that before you spend in the wrong order.
  • You may not need the upgrade at all. NEC 220.87 lets an existing dwelling be sized from twelve months of actual metered demand rather than a calculated load, and real houses draw far less than the calculation predicts. Ask your utility for a year of interval data and have it run that way first. Two cautions so this does not backfire: the demand tile in a TEP online account shows on-peak demand only, which is not the annual maximum the code asks for — you want the formal usage-data release — and 220.87 proves CAPACITY and nothing else. It does not create empty breaker spaces, and it does not make an obsolete panel, or one whose breakers have a documented failure history, safe. Those are separate questions with separate answers — and where the era makes a brand worth checking, the report above says so on its own.

A finalled HVAC permit from 2017 is on record, so the equipment is inside its expected life and we are not pricing a replacement.

What the record cannot tell us
  • Whether the service is already 200 A. Nothing in the public record says so, and the number is stamped on the main breaker handle.
  • Whether the panel can stay where it is. A panel in a closet, over stairs or behind a door has to move, and that alone adds $1,500 to $5,000.
  • Whether the service comes in overhead or underground. This is priced as overhead; an underground service with an adequate lateral is a few hundred dollars cheaper, and one with an undersized lateral is thousands more.

Price it for your house — change the assumptions (the panel’s location, the duct, the tonnage, whether the service is overhead or underground) and watch the number move.

Solar on this property

Solar was permitted here in 2018 and passed final inspection. What that means if you add anything: the panel’s busbar already carries the solar backfeed, so an EV charger, a heat pump or a bigger air conditioner has to fit what is left under the 120% rule in NEC 705.12, not just the service size. Check the busbar rating on the panel label before you add a load.

A battery, more panels or an EV charger tied to the solar is new permitted work, and anything that changes the solar connection usually needs a new interconnection application with TEP. TEP credits exported surplus at its RCP rate — about 5¢/kWh for new applications, locked for 10 years — so sizing to the home’s own use matters more than filling the roof.

Flood and drainage

The federal flood map and the local one are not the same map, and they do not always agree. FEMA’s is the insurance map; the City of Tucson regulates against its own, and that is the one a permit here is judged against.

The record behind this read

Parcel
138041470
Year constructed
1951 (county record)
Permitting authority
Tucson
Zoning
R-1
Living area
994 sq ft
Cooling
Evaporative (assessor record; a 2017 permit names refrigerated equipment, and this report goes by the permit)
Heating
Forced Air
Electrical service
No service or panel permit on record. A 1951 house likely still has its original 60 to 100 A service. (the era estimate is from the year built, 1951 — not a measurement)

Living area, cooling and heating come from the Pima County Assessor’s file published 28 Jan 2026. Check any row against Pima County’s own parcel record ↗.

What this means for work here

The most recent permit with evidence of issuance is dated 2018. City records show the permit was finalized. The permit covers only the work described in that record.

What that reading rests on. The issuing offices hold 3 building permits for this parcel dated between 2017 and 2018. Two trade permits and one solar permit. 2 of them carry a final inspection; the other one was issued, expired or is still open, which is not the same as work completed.

Street and utility work at this address. The City’s file also shows one right-of-way or utility permit here (2023) — work in the street or on a utility’s lines, not on the building, so it is left out of the counts above.

Go straight to the records

Each link opens the issuing office’s own file for that record — dates, scope, status and inspections are theirs to publish, and they are all on the other side of these links.

Permit records courtesy of the City of Tucson — each link opens the City’s own file. The files are held by City of Tucson permit record (PRO) ↗ — search the parcel number 138041470.

See an error? Report a correction · About this data.

Utility and upgrade pathElectric service here is Tucson Electric Power (TEP). A service or panel upgrade needs a TEP meter release and has to meet TEP’s service requirements — meter height and location, clearances, and the point of attachment. See TEP new-service requirements and the TEP standards notes.

In the public record: All homes in 85756 · Homes by ZIP code · Commercial property in 85756 · Permit data by neighborhood

Planning work at this home?

Arizona Electrical Solutions — electrical, HVAC, underground, design-build and general contracting in Tucson (four Arizona ROC licenses). The address, parcel and this report travel with your request.

Get a free panel check

Want a plain-English brief of this record first?

The contractor’s read is a plain-English brief of the record above, written by AI — what it shows across electrical, mechanical and the building itself, what is missing for the era, and what to verify on site.

How this property compares nearby

Built in 1951 — earlier than about 98% of the 10,190 homes in ZIP 85756. 994 sq ft of living area — below this ZIP’s median of 1,602 sq ft. Properties on W CALLE DE CASAS LINDAS hold 164 City permits on record, 83 of them since 2022.

Counts and years from the same public records.

How this report was built

This is a reading of public records for parcel 138041470 — 3 City permits on file from 2017 to 2018 and 1 street or utility permit — assembled from the Pima County parcel file and the City of Tucson’s published permit layers together with the City’s own migrated permit archive. City of Tucson permit records go back to the mid-1990s, with fewer before 2006, when the City’s older paper files were only partly digitized. The construction year, living area, cooling, heating, roof and walls on this page come from our saved copy of the Assessor’s own published data file (dated 28 Jan 2026). The sewer connection file and the flood map were not read for this snapshot. A permit that is absent here may predate the digitized record or sit in a system this snapshot did not read. This record was built 13 Nov 2026 from the City’s permit export of that day.

What this report is and is not. This is a screening report written by Arizona Electrical Solutions from public records — the year the building went up, how it is classified and what has been permitted. It is not an inspection, an appraisal, a floodplain determination, or engineering, legal or purchasing advice, and nothing in it confirms what is installed at this address: a permit shows what was permitted, a missing permit does not mean nothing was done, and era notes describe what was common when the building went up, not what is in this one. Price figures are estimates, not quotes. The issuing agency’s own record is the official one and controls over anything summarized here — every permit links to it. Only someone looking at the panel can confirm the service size, the panel brand or the wiring.

Written and maintained by Arizona Electrical Solutions, LLC, a licensed Tucson contractor (ROC 276948 CR-11 electrical, ROC 326401 CR-39 HVAC, ROC 329360 KB-1, ROC 312437 KA).