Field Guide • Power & Distribution

How to Install a Commercial Subpanel

Updated July 16, 2026 • Written by the field team at Arizona Electrical Solutions. All field guides →

A subpanel — properly, a panelboard fed from existing service or distribution equipment — puts circuit capacity where the load actually is. On commercial jobs that means a tenant improvement adding a kitchen, a shop adding machine tools, or a suite that's out of breaker spaces. Land one feeder and distribute locally instead of home-running twenty branch circuits across the building.

The work splits into two halves: engineering (load calc, feeder and OCPD sizing, fault-current check) and installation (mounting, raceway, terminations, labeling). Most subpanel red tags come from the grounding side, so this guide leans hard on the four-wire feeder and the isolated neutral. Everything here assumes a subpanel in the same building as its supply — separate structures pull in NEC 250.32 and are a different conversation.

Safety first. This work is for qualified, licensed electricians only. Before touching a conductor, de-energize the source, apply lockout/tagout, and verify absence of voltage with a tester confirmed against a known live source. Wear PPE appropriate to the incident energy per NFPA 70E — gear near the service carries serious arc-flash energy. Commercial panel work requires a permit in nearly every jurisdiction, and the locally adopted NEC edition and amendments govern — confirm with your AHJ.

Commercial Subpanel Installation — The Isolated-Neutral Rule Simplified one-line wiring diagram. A main service panel on the left shows the neutral bus bonded to the enclosure by the main bonding jumper, which exists only at the service. A four-wire feeder (two or three ungrounded conductors, a neutral, and an equipment grounding conductor sized per NEC 250.122) runs to a subpanel on the right. In the subpanel the neutral bar is isolated on standoffs with no bond screw installed, while a separate ground bar is bonded to the enclosure. Branch circuits leave the subpanel. Per NEC 250.24(A)(5) the neutral-to-ground bond exists only at the service. Working space per NEC 110.26 is a minimum of 30 inches wide by 36 inches deep. Commercial Subpanel Installation — The Isolated-Neutral Rule MAIN SERVICE PANEL Neutral bus MBJ — bonded here ONLY Feeder breaker SUBPANEL 4-WIRE FEEDER Ungrounded (2 or 3) Neutral EGC — sized per 250.122 Main lugs Branch circuits Neutral bar ISOLATED — no bond screw Ground bar — bonded to can Neutral-to-ground bond exists ONLY at the service — 250.24(A)(5) Working space: 30 in wide × 36 in deep min — 110.26 Simplified educational diagram — always verify against the adopted NEC edition and the AHJ.
Simplified concept diagram for training and illustration — not a construction document. Equipment layouts vary; manufacturer instructions and the locally adopted code govern.

What you'll need

  • Panelboard with main lug or main breaker kit, matched to system voltage and phase
  • Feeder breaker for the supply panel, correct frame and AIC rating
  • Feeder conductors — three phases, neutral, and a separate equipment grounding conductor
  • Raceway (EMT, rigid, or PVC as the environment dictates) with fittings and straps
  • Equipment ground bar kit for the subpanel (often sold separately)
  • Torque screwdriver and torque wrench covering the lug ranges on the job
  • Insulated hand tools, voltage tester, and megohmmeter
  • Phase tape for conductor identification per NEC 215.12(C)
  • Typed circuit directory card and panel label stock

Code references

NEC 215.2(A)Minimum feeder conductor ampacity, including the 125 percent factor for continuous loads.
NEC 250.24(A)(5)Neutral-to-ground bonding occurs only at the service — never downstream in a subpanel.
NEC Table 250.122Equipment grounding conductor size based on the rating of the feeder overcurrent device.
NEC 110.26Working space (width, depth, headroom) and dedicated equipment space around the panel.
NEC 110.9Interrupting ratings must equal or exceed the available fault current at the equipment.
NEC 408.4Circuit directory requirements and marking the source of supply on the panel.
NEC 110.14(D)Terminations must be torqued to the marked value using a calibrated tool.

Section numbers follow the 2023 NEC; the edition adopted by your jurisdiction governs.

Step by Step

How to Install a Commercial Subpanel

1. Run the load calculation first

Size the panel from an Article 220 load calculation, not a guess. Add up the loads it will serve: lighting per Table 220.42(A) or the actual connected load, whichever is larger (the table lived at 220.12 before the 2023 edition), receptacles per 220.14 with the Table 220.47 demand factors (Table 220.44 in the 2020 edition), motors per 430.24. Continuous loads — on for three hours or more, meaning most commercial lighting — count at 125 percent per 215.2(A)(1) and 215.3.

Then leave room. A panel calculated at 92 percent of its rating on day one is a callback — if the calc lands near the top of a standard size, step up.

2. Size the feeder and its overcurrent device

The feeder OCPD lives at the supply end — a breaker in the upstream panel or distribution board — and per 408.36 the panelboard must be protected at no more than its rating. Simplest practice: 100 A breaker for a 100 A panel, 225 A for a 225 A panel.

Pick conductors from Table 310.16 at the 75°C column for typical terminations, after any ambient or fill adjustments from 310.15. For a 100 A feeder that's 3 AWG copper; for 125 A, 1 AWG copper. Check voltage drop too — the informational note to 215.2(A) suggests keeping feeder drop to 3 percent. Not enforceable, but a long run at full load will make you wish you'd listened.

Size the EGC from Table 250.122 by the feeder OCPD rating: 8 AWG copper for a 100 A device, 6 AWG copper for over 100 A through 200 A. Upsize the phases for voltage drop and 250.122(B) requires upsizing the EGC proportionately.

3. Verify the fault current and AIC rating

Every breaker in the new panel needs an interrupting rating at or above the available fault current at its line terminals — that's 110.9. Get the fault current from the utility or the service documentation, then account for your feeder run; fault current drops with conductor length.

Standard 10 kAIC breakers cover many locations, but a panel close to a large transformer can see well above that. If fault current exceeds the breaker rating, use higher-AIC devices or a series-rated combination per 240.86 — valid only for manufacturer-tested, listed combinations. Note that 110.24 requires the maximum available fault current and calculation date to be field-marked on service equipment (other than dwellings); documenting it at the new panel as well is good practice and commonly spec-required.

4. Locate the panel for working clearance and dedicated space

NEC 110.26(A) sets the minimums: working space at least 30 inches wide (or the equipment width, whichever is greater), 36 inches deep for Condition 1 at 150 V to ground or less, and 6.5 feet of headroom. Depth goes to 42 or 48 inches at higher voltages with grounded or exposed live parts opposite — check Table 110.26(A)(1). Hinged panels must open at least 90 degrees.

Don't forget 110.26(E): the panel's footprint, from the floor to 6 feet above the equipment or to the structural ceiling, is dedicated electrical space — no duct, no plumbing, no foreign systems. Fight for it at rough-in; the mechanical trades will take it if you don't.

5. Mount the panel and run the feeder raceway

Set the enclosure plumb and anchored to structure — strut rack on masonry, or backing in a framed wall. Keep the highest breaker handle at or below 6 feet 7 inches per 240.24(A). Size the raceway per Chapter 9, Table 1 fill (40 percent for three or more conductors).

Pull all four feeder conductors together: three phases, neutral, EGC. Where the building has both voltage systems, identify feeder conductors by phase and system per 215.12(C) (branch circuits fall under 210.5(C)) — commonly brown-orange-yellow at 480Y/277, black-red-blue at 208Y/120 — document the scheme at the panel and keep it consistent building-wide.

6. Terminate: isolated neutral, bonded equipment ground

This is the step that fails inspections. The neutral-to-ground bond happens in one place: the service disconnect (250.24(A)(5)). Downstream, neutral and ground stay separated. The subpanel neutral bar must be isolated from the can — do not install the green bonding screw or strap that ships in the box. Leave it in the bag.

Install a separate equipment ground bar bonded to the enclosure; land the feeder EGC and all branch EGCs there, and the feeder neutral on the isolated bar. Bond the neutral downstream and neutral current will return on the EGC, raceway, and every metallic path in parallel — a shock hazard and an instant red tag.

Torque every termination to the value marked on the equipment, with a calibrated tool, per 110.14(D). Values differ by lug and conductor size — use the label, not memory.

7. Test before you energize

Megger phase-to-phase, phase-to-ground, and neutral-to-ground on the dead feeder with load disconnected. A neutral-to-ground reading near zero ohms means a downstream bond — find it before energizing. Verify torque marks on every lug and that the bonding screw is out.

Energize the feeder breaker with the cover on and no load, verify voltage phase-to-phase and phase-to-neutral at the lugs, then load circuits one at a time. Confirm rotation on three-phase loads before releasing equipment.

8. Fill out the directory and label the panel

NEC 408.4(A) requires every circuit to be legibly identified with enough detail to distinguish it from all others, and the description can't depend on transient occupancy — 'Bob's office' fails, 'receptacles, NW offices 210–214' passes. Type it; handwritten directories age badly.

408.4(B) requires marking where the supply originates — 'Fed from Panel DP-1, Breaker 14, Electrical Rm 101' on the can. Add the available fault-current documentation (the 110.24 field marking itself is required at the service equipment) and any required arc-flash label.

Watch Out

Common mistakes

  • Installing the factory bonding screw in the subpanel neutral bar, putting neutral current on every grounding path in the building.
  • Landing branch EGCs on the neutral bar because the panel shipped without a ground bar — buy the ground bar kit.
  • Running a three-wire feeder when the design called for a wire-type EGC — pull the fourth conductor.
  • Installing 10 kAIC breakers where available fault current is higher — a 110.9 violation and a real hazard.
  • Letting the mechanical trades hang duct in the dedicated space above the panel, which 110.26(E) reserves for electrical.
  • Forgetting to upsize the EGC when phase conductors are upsized for voltage drop, as 250.122(B) requires.
  • Writing a vague, penciled directory that fails 408.4(A) and guarantees somebody troubleshoots blind in five years.

FAQ

Frequently asked questions

Why can't the neutral be bonded at a subpanel?

The NEC allows the neutral-to-ground bond only at the service disconnect. Bond them again downstream and neutral current flows back on the equipment grounding conductor, raceways, and enclosures in parallel, putting current on things people touch.

Does a commercial subpanel always need a four-wire feeder?

You need the phase conductors, a neutral if the panel serves line-to-neutral loads, and an equipment grounding conductor. The EGC can be a listed metallic raceway in some designs, but a wire-type EGC pulled with the feeder is standard practice and what most specs call for.

What size ground wire does a 100 A subpanel feeder need?

Per NEC Table 250.122, a feeder protected at 100 amps requires an 8 AWG copper equipment grounding conductor. If the phase conductors are upsized for voltage drop, the EGC must be upsized proportionately.

How much clear space does the code require in front of a panel?

NEC 110.26 requires working space at least 30 inches wide, 36 inches deep for the most common condition, and 6.5 feet of headroom. The footprint above the panel up to 6 feet or the structural ceiling is dedicated to electrical equipment only.

What does the AIC rating on a breaker mean?

AIC is the ampere interrupting capacity — the maximum fault current the breaker can safely interrupt. Every breaker must be rated at or above the available fault current at its terminals, so know that number before ordering breakers.

Do I need a permit to add a subpanel in a commercial building?

Almost certainly yes. Adding a panelboard is permit work in virtually every jurisdiction and gets inspected under the locally adopted NEC edition. Check with your building department first.

Do this work every day?

We're hiring electricians and HVAC techs on commercial projects across Arizona — see open positions. Need this done on your project instead? We self-perform it.

Request a Bid